November 12, 2026
In November 2024, Huntley Park District voters approved an $18 million bond for park and facility work, to be spread across several years starting in 2025. Two years later, the most visible new project is already closing for the season. The eight fenced pickleball courts at Deicke Park close from about mid-November until mid-March. With turf, a pool heater and a park renovation finished in 2026, the bigger winter story is a golf building at Pinecrest that is under construction this season and planned to run year-round.
The referendum question listed dozens of line items in seven groups, from security cameras at Stingray Bay to a new splash pad. Most were repairs and repaving. The Park District's Plan to Play page gives an estimate for each item, and its capital projects tracker records progress. Here are the pieces residents have seen move in 2026:
| Project | Referendum estimate | Status as of mid-November 2026 |
|---|---|---|
| Artificial turf infields, Tomaso Sports Park | $1,200,000 | Completed January 2026 |
| Stingray Bay pool heater | $160,000 | Completed May 2026 |
| Ol' Timers Park update | $600,000 | Marked complete September 2026 |
| Multi-court pickleball | $860,000 | Eight courts at Deicke Park, closing for winter |
| Replace three bridges at Pinecrest Golf Course | $550,000 | Scheduled for fall 2026 |
| Golf entertainment | $1,500,000 | Construction window September 1 to December 1, 2026 |
The finished projects are mostly upgrades to places residents already used. At Tomaso Sports Park, Field A, the Amazon Field, is now fully artificial turf. Fields B, C and D, named ARG, TruGreen and Niko's, have turf infields with natural grass outfields. The work also added a padded backstop wall, new netting and new fencing, and Fields E and F got new infield mix. At Ol' Timers Park, the work added a new playground, a new wiffle-ball field and a prairie and wetland natural area southwest of the park. The District said frequent rain had delayed the plantings and that they would go in this fall as water levels went down. A separate $384,500 matching grant from the state's Open Space Land Acquisition and Development program also went toward that renovation.
Smaller paving projects are moving too. Warrington Park Trail is being converted from limestone to pavement for better accessibility. The District's schedule called for asphalt late in the week and a Friday, October 30 opening.
The Deicke courts sit in the middle of Deicke Park, just south of the REC Center. The District's October 28 update said paddle holders and windscreens were on the way and the remaining construction fencing would be removed. The seasonal closure comes right after that work, so the windscreens get their first real use in spring.
Two indoor options take over for the winter, and both are run by the Park District.
The Pinecrest simulator page has current booking details. The simulators are an existing service at the clubhouse and are separate from the new building going up beside the driving range.
According to the Northwest Herald's June 2026 report, the golf entertainment center is a 3,670-square-foot building directly east of the Pinecrest driving range. It will have eight open bays and three seasonal bays. The paper reported that Park District Executive Director Scott Crowe told the Village Board each bay would have seats and a high-top table at the back, and the ball tracking would use the same technology as Topgolf. The Herald also compared the model to Bridges of Poplar Creek Country Club in Hoffman Estates.
The winter question is part of the design. The Herald reported that the plan is to run year-round. The center won't have Topgolf's heated turf or underground ball return, so Crowe said it may close temporarily after heavy snow that sticks around or during a strong, cold north wind. The pickleball courts close on a set calendar. The golf center will close only on bad-weather days.
The Herald's report also described how a visit would work:
On the District's tracker, the construction window runs from September 1 to December 1, 2026, with completion estimated for winter 2026. At its June 24, 2026 meeting, the Park Board authorized the executive director to sign and acknowledge the Village ordinance for the project. Bridge work is happening on the same property. The fall plan replaces the bridge on Hole #1 and the wood decking on several sound bridges on the back nine.
The golf center is the largest new project this winter. The next one is much bigger in land area. The Park District and the Village of Huntley worked together to secure 153 acres for a future community park. In October, the Illinois Association of Park Districts gave both agencies its Intergovernmental Cooperation Award at the Best of the Best Gala in Wheeling. Village President Tim Hoeft said in the District's announcement that the Village spotted the opportunity because it knew the Park District was looking for land for a community park.
Phase 1 is budgeted at $1.8 million, and a $600,000 state OSLAD grant covers part of it. Planned amenities include athletic fields, trails, community gardens, a shelter and a ninja course. Construction is scheduled to start in spring 2027. The District held a park naming event on October 29 at the site, 11251 Kreutzer Road. Kreutzer Road Park appears on the capital tracker as a spring 2027 groundbreaking.
The golf center is scheduled to finish this winter, the Deicke courts reopen around mid-March, and work at Kreutzer Road starts in the spring.
Until then, most of the District's winter activity happens indoors and on a short run of December dates. The Park District's December 2026 calendar lists:
There's also one outdoor option that depends on the weather. The pond rink at Deicke Park, east of the REC Center, opens only when District staff decide the ice is safe. It's a short walk from the courts that are now closed for the season.
Park projects like the turf at Tomaso, the courts at Deicke and the work at Pinecrest are part of what a Huntley address offers, and we include them when we present a home. If you'd like to know how your home compares this winter, Christine Currey and the Currey Koertgen Team can prepare a valuation that covers the nearby parks along with the house. How Much Is Your Home Worth?
Whether you're buying, selling, or investing, we’re here to help you navigate the market with confidence. With expert negotiation, strategic marketing, and a client-first approach, we’ll get you the best results.